Brief Description
Rebuilding of the Hotel Funimation III at Katschberg
Scope of Work |
|
|
|
|---|---|---|---|
Demolition Cubature | ca. | 450 | m3 |
Demolition Floor Covering | ca. | 5000 | m2 |
Formwork | ca. | 4.600 | m2 |
Concrete | ca. | 760 | m3 |
Steel | ca. | 80 | to |
Cutting Areas | ca. | 500 | m2 |
Steel Profile | ca. | 15 | to |
Client
RCB Beteiligungs GmbH
9863 Rennweg, Katschberghöhe 20
Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
Villach Branch
Planning
Michaeler & Partner Planning und Engineering GmbH
9020 Klagenfurt, Kurandtplatz 1
Contact: Mr Bmstr. [Master Builder] Herbert Kusternigg
Contract Price
€ 1.715.000,00 net
Construction Time
03/2008 – 07/2008
Site Manager
Mr Ing. Georg Tschernitz
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]