References > Building Constr. > Industry > MAN Steyr

MAN Steyr, Trailer Yard and Gate 2

Brief Description
Rebuilding of the trailer yard with 2,700 m² of concrete area and 4,000 m² of asphalt area. Remodelling of the entrance at Gate 2. New parking space and approach ramp at Gate 2. Concreted footpath from the fire service to Hall 9. Tube bridge made of reinforced concrete prefabricated parts from the company HABAU.

Scope of Work
Total Site Management Work without Earthwork:
Reinforced Concrete and Asphalt Work:
Mixture 2 to

Client
Bernegger GmbH
4591 Molln, Gradau 15
Contact: Mr Christian Hackl

Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
Steyr Branch

Planning
tbbw  
Technisches Büro für Bauwesen
4533 Piberbach, Dorfplatz 5

Total Order Value
€ 1.903.571,83 net

Contract Price
€ 1.022.557,92 net

Construction Time
07/2008 – 11/2008

Site Manager
Mr Ing. Oswald Aichmayr

Fit For A Lifetime

With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]

A Young Company Introduces Itself

H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]

H&F Never Stands Still

At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]