Brief Description
Laying of overhead pipelines leading through the forest.
Scope of Work
8.5 km laying of buried cable (bundle of 3) in rocky ground, approx. 30 m line DN 300 under the mountain pasture, and varied asphalting of trenches.
Client
Energie AG Oberösterreich Tech Services GmbH
4020 Linz, Böhmerwaldstraße 3
Contact: Mr Bmst. [ Master Builder] Stefan Maier
Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
4030 Linz, Kotzinastraße 4
Planing
Energie AG Oberösterreich Tech Services GmbH
4020 Linz, Böhmerwaldstraße 3
Contract Price
€ 200.000,00 net
Construction Time
04/2009 – 06/2009
Site Manager
Mr Ing. Björn Ortner
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]