ABA Neustadtl/Donau, BA06 u. BA07

Brief Description
Vacuum and gravity sewer, clarification plant

Scope of Work
Main and Branch Sewer DN32-DN500  approx. 7.000m1
Trench Excavation  approx. 11.000m³
Floor Class 6-7  approx. 2.500m³
Prefabricated Shafts DN1000  approx. x 50
Prefabricated Pumping Station DN1500  x 1
Clarification Plant 10,6*10,6*5,3 m1  x 1.
Pipe Bridges DN325  approx. 40 m1
Asphalted Roads and Paths  approx. 5.000m²

Client
Market Town of Neustadtl/Donau
3323 Neustadtl/Donau, Marktstraße 16
Contact: Mr Deputy Mayor Rosenthaler

Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
St. Pölten Branch

Planning
IKW Voglauer, Mader & Schlöglhofer ZT-GmbH

Contract Price
approx. 1.650.000,00 € incl. VAT

Construction Time
07/2006 - 05/2008

Site Managers
Mag. Ing. Horak Walter and DI. Zeilinger Günter 

A Young Company Introduces Itself

H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]

H&F Never Stands Still

At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]

Fit For A Lifetime

With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]