A7 MÜHLKREISAUTOBAHN - BINDERMICHL

Brief Description
Lowering and enclosure of the autobahn in the Bindermichl section.

Scope of Work
Concrete: approx. 200,000 m³
Steel: approx. 20,000 to
Earth-Moving: approx. 800,000 m³

Client
ASFINAG Autobahnen- und Schnellstraßen-Finanzierungs-AG
1010 Wien, Rotenturmstraße 5 – 9
Awarding Office: Upper Austrian Federal State Government, 4010 Linz, Bahnhofplatz 2

Contractor
ARGE Strabag – Alpine – Held & Francke – Porr

Planning
ZT Büro Kirsch-Muchitsch & Partner
4010 Linz, Kapellenstraße 13

Contract Price
approx. € 110 million (Share HF: € 22 million)

Construction Time
10/2003 – 12/2005

Project Manager
Mr Ing. Hanser (Fa. Strabag)

Site Manager
Ing. Kaltenbrunner (Company: Alpine) – Bridge Construction
DI Ecker (Company: Porr) – Tunnelling Under East and West Pipes
DI Knoll (Company: Porr) – Earthwork
Mr Kerschbaumer (Company: Held & Francke) – Enclosure and Sub-Tunnel

H&F Never Stands Still

At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]

Fit For A Lifetime

With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]

A Young Company Introduces Itself

H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]