Brief Description
New construction of underground garage at Bahnhofplatz in Villach
Scope of Work
Trench Excavation approx. 30,000 m³
Building Underpinning HDBV, Columns DN 150 approx. 700 m.
Sprayed Concrete Protection approx. 1.000 m²
Reinforced Concrete approx. 5.500 m³
Concrete Reinforcement approx. 800 to
Covering Work Parking Areas Underground Garage approx. 6.000 m²
Client
Draupassagen Garagen GmbH
9500 Villach, Rathausplatz 1
Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
Villach Branch
Planning
Architekt Dr. Lengger ZT GmbH
9500 Villach, Ossiacher Zeile 7
Contact: Mr Arch. DI Kreilitsch
Contract Price
€ 3,000.000,00 net
Construction Time
10/2007 – 06/2008
Site Manager
Mr DI Josef Lagger
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]