References > Underground Constr. > Power Station Construction > Small Power Station Gurk

Small Power Station Gurk

Brief Description
Small Power Station Gurk
Construction of a powerhouse incl. headrace, sand trap, intake structure and fish bypass  

Scope of Work
Construction Trench Excavation  approx. 10.800 m³
Ripraps  approx. 1.500 to
Shoring with Steel Sheet Piles  approx. 700 m²
Concrete  approx. 2.100 m³
Concrete Steel  approx. 170 to
Formwork  approx. 5.300 m²  

Client
Energieversorgung Pöckstein GmbH
9313 St. Georgen / Längsee, Schlossallee 6
Contact: Mr Dr. Lackinger  

Contractor
Held & Francke Baugesellschaft mbH & Co KG
Villach Branch 

Planning
Büro DI Peter Schallaschek
9020 Klagenfurt, Viktringer Ring 9
Contact: DI Peter Schallaschek 

Contract Price
€ 900.000,00 net  

Construction Time
03/2007 – 11/2007  

Site Manager
Ing. Georg Tschernitz

H&F Never Stands Still

At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]

Fit For A Lifetime

With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]

A Young Company Introduces Itself

H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]