References > Underground Constr. > Power Station Construction > Power Station Schwarzach

Power Station Schwarzach Contract Section 1

Brief Description
In general, the weir plant and sand trap system can be divided into the following construction sections

Weir plant with fish ladder (orographically left), HW weir, secondary outlet, Tyrolean weir and command reservoir (orographically right) cross channel and sand trap system incl. flushing channel.

The Schwarzach is slightly dammed, by approx 2.8 m, by a solid weir with a total width of 21 m. The weir has various weir crest heights in the different sections. The damed-up water passes via a cross channel approx. 25m long that crosses beneath the Hopfgartner Grabenbach, into the sand trap system located at the left bank of the Schwarzach, which consists of the inlet channel, the two sand trap chambers, the flushing chamber with flushing channel and the extraction overfall with the control rooms where the solids carried from the Schwarzach are separated from the works water. From the extraction overfall, the works water goes into the extraction basin, that acts to regulate the turbines and as an accumulator for operational transfers.  

Scope of Work
Earthwork:  31.000 m³

Earth-Moving   Protection: 
1.200 m²  SPB 
2.400 m IBO Anker

Concrete Construction:
5.200 m³ Concrete 
9.700 m² Formwork
410 to Concrete Reinforcement

Road Construction:
750 m³ Frost Wall Material
1.500 m² Asphalt  

Client
TIWAG 
Tiroler Wasserkraft AG
6010 Innsbruck, Eduard Wallnöver Platz 2
Contacts:
Mr Dr. techn. Helmut Schönlaub  Project Manager
Mr Dipl. Ing. Bernd Baumgartner  Local Site Supervision 

Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
Tirol Branch 

Planning
TIWAG
Tiroler Wasserkraft AG
6010 Innsbruck, Eduard Wallnöver Platz 2  

Contract Price
€ 2.200.000 net   

Construction Time
04/2005 – 12/2006  

Site Manager
Mr Ing. Thomas Buchberger

Fit For A Lifetime

With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]

H&F Never Stands Still

At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]

A Young Company Introduces Itself

H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]