Arge New Building Seebach Tunnel

Brief Description
A 445 m-long arch-shaped road tunnel was constructed in the area of L16 Pitztalstraße due to the constantly threatening danger of rockfalls and avalanches.

The concrete vault was constructed in open cut in 37 sections with an individual length of approx. 12 m and subsequently covered.

For a length of approx. 660 m, the existing road was removed and adapted to the new protective construction.

Scope of Work
Earthwork
Removal:  approx. 20.000 m³
Fill:  approx. 47.000 m³

Concrete Construction
Concrete:  approx. 7.000 m³
Concrete Reinforcement:  approx. 600 t

Road Construction
Frost Wall:  approx. 2.800 m³
Asphalting:  approx. 4.500 m²  

Client
Office of the Tyrolean Government
National Construction Agency
Bridge and Tunnel Construction Department
6020 Innsbruck, Herrengasse 1-3
Contact: Mr DI Günter Guglberger

Local Site Supervision: BBA Imst Mr Moser Gebhard  

Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
Innsbruck Branch 

Planning
DI Karl Sporschill
Civil Engineer for Construction
6020 Innsbruck, Riedgasse 19  

Contract Price
€ 3.483.919,92 net  

Construction Time
October 2006 – May 2008  

Site Manager
Mr DI(FH) Roland Sumper  

Arge Share in Euro / %
€ 1.741.959,96 net

H&F Never Stands Still

At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]

Fit For A Lifetime

With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]

A Young Company Introduces Itself

H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]