Specifications::
The construction measure essentially comprises the construction work to produce the road tunnel and the accompanying road construction work. The building measure includes the excavation of the tunnel, the crossways up to approx. 12m before the escape gallery (incl. the complete interior work, also at the escape gallery), the producing of the ventilation shaft, the open cut construction at the north and south and the producing of the secondary structures.
The secondary structures include:
Brief Description
Total Contract Section Length: 3.580 m
Total Tunnel Length: 2.150 m
Tunnel Open Cut: 710 m
Tunnel Mined Construction: 1.440 m
Earthwork/Road Construction + Ramps: 1.430 m
Preliminary Cutting South + North Open Cut: 710 m
Scope of Work
Concrete: approx. 90.000 m³ (incl. sprayed concrete)
Structural Steel: approx. 1.800 to
Excavation: approx. 300.000 m³ (incl. tunnel excavation)
Client
Office of the Salzburg Regional Government; Dept. 6/2 - Road Construction
Mr HR DI Andorfer; Mr DI Dr. Hittenberger Roland
Mr Walter Vlasak
Contractor
ARGE Tunnel Henndorf
Wayss Freytag
Held & Francke Baugesellschaft m.b.H. & Co KG
HABAU Hoch- u. Tiefbaugesellschaft mbH
Planning
Spirk & Partner; Geoconsult
Contract Price
approx. € 32,8 Mio. net
Construction Time
05/2006 – 06/2009
Site Manager Tunnel, Mined: Dipl. Ing. Tobias Mayer (Wayss & Freytag)
Deputy Site Manager Tunnel, Mined: Dipl. Ing. Oliver Glück (HABAU)
Site Manager Open Cut & Earthwork: Dipl. Ing. Werner Pfeiffer (Held & Francke)
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]