Brief Description
New construction of the Getzing bypass (B 127, Rohrbacher Straße), contract section length 2.250 km, incl. production of four bridge constructions, 2.550 km farm and accompanying paths. Reconstruction of the goods route Humenberg and Iglmühlstraße and/or Sportplatzstraße from 0.660 km, furthermore construction of 3 retention and 2 storage basins and laying of 830 m water supply conduits. The contract section is located between Arnreit and Neundling.
Scope of Work
Key Data Road Construction
Removal 135.500 m³
Rock Removal 40.000 m³
Embankment Fill 122.000 m³
Soil Improvement 16.000 m³
Humus Work 8.500 m³
Drainage 9.870 m1
Filter Gravel 2.200 m³
Puddle and Soil Filter 1.050 m³
Water Transfer Conduit 830 m1
Cable Protection Pipes 460 m1
Shafts 230 Stk.
Concrete and Walling Work 145 m³
Subgrade 52.000 m²
Frost Protection and Upper Substrata 37.200 m³
Edge Enclosures 550 m1
Granite Paving 400 m²
Asphalt Construction 36.000 m² = 18.600 to
Noise Control Walls 1.400 m²
Guard Rails 2.400 m1
Veterinary and Safety Fence 3.200 m1
Ripraps 610 to
Key Data Bridge Construction
Foundations, Abutments, Pillars 1.710 m³
Supporting Structure and Edge Beams 420 m³
Steel 145 to
Client
Office of the Upper Austrian Government, Road Construction Department
4021 Linz, Bahnhofplatz 1
Contact: Mr Ing. Aistleitner
Office of the Upper Austrian Government, Bridge Construction Department
4021 Linz, Bahnhofplatz 1
Contact: Ing. Leta
Contractor
ARGE Bypass Getzing
Held & Francke Baugesellschaft m.b.H & Co KG, Kotzinastraße 4, 4030 Linz
Alpine Bau GmbH, Sophiengutstr. 20, 4021 Linz
Brüder Resch Hoch- und Tiefbau Ges.m.b.H. & Co KG
Dreisesselbergstr. 1, 4160 Aigen-Schlägl
Planning
Schimetta Consult, Ziviltechniker Ges.m.b.H
Landwiedstr. 23, 4020 Linz
Contract Price
€ 6.475.000,00 net
Construction Time
07/2008 – 09/2009
Site Managers
Held & Francke und ARGE: 2008 Dipl. Ing. Klaus Gruber
Held & Francke und ARGE: 2009 Siegfried Lumetsberger
Held & Francke: Ewald Hehenberger, Water Transfer Conduit
Alpine: Ing. Alois Stallinger, Road Construction
Brüder Resch: Ing. Franz Groiß, Bridge Construction
Foreman
Held & Francke und ARGE: Helmut Steininger
Held & Francke: Franz Litzelbauer, Water Transfer Conduit
Alpine: Josef Schneeberger, Road Construction
Brüder Resch: Ewald Bauer, Bridge Construction
Arge Share in Euro
HF Share: € 3.250.000,00 net
Miscellaneous
The entire transportation of materials within the construction site, such as removal and moving for embankment fill and to the dump, furthermore all material deliveries, such as of concrete, steel, gravel, asphalt, pipes, filter gravel, granite blocks, noise control walls, guard rails, shaft parts and the production of interim solutions for traffic handling and many other items amounted to approx. 915.000 to, which is approx. 45,750 4-axle HGVs. If one were to place these end-to-end, that would be a length of approx. 395 km, which is almost from Vienna to Munich on the autobahn.
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]