Brief Description
Remodelling of the entire outdoor facility at the new construction of the ice rink on Untere Donaulände. Performance as Arge HF- Strabag- Alpine. Arge carried out the demolition, earthwork, canalisation, paving, milling, asphalting, lighting and humus work and var. secondary work.
Scope of Work HF
Paving Work:
EPL 50/50/5 on Chippings approx. 1.200 m²
SInfiltration Paving on Chippings approx. 460 m²
Granite Blocks LS3 approx. 300 m1
Granite "Köpfel" Stone GPS1+GPS2 approx. 700 m1
Granite Kerbstone ROA6 approx. 70 m1
Tactile Guide System approx. 30 m²
Re-laying Concrete Block Paving from Existing Construction approx. 300 m²
Concrete Upstanding Kerb 12/20 approx. 100 m1
Milling and Asphalting Work:
Fine Covering Milling approx. 300 m²
Covering Work AC8deck approx. 2,600 m²
Bituminous Substratum AC32/22trag approx. 1,000 m²
Ground Marking Work:
Line Label approx. 1.000 m1
Pillars 3 m high approx. x 15.
Div. Block and Special Markings
Bicycle Stands:
Flat Steel Bicycle Leaning Stands x 100
Bicycle Stand System Kappa x 140
Client
Linz Service GmbH represented by Management Linz GmbH
4021 Linz, Wiener Straße 151
Contact: Mr Ing. Berner and/or Mr BM Ing. Ring
Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
4030 Linz, Kotzinastraße 4
Planning
Riepl Riepl Architekten
Contact: Mr DI Edelbauer
4020 Linz, Ok-Platz 1A / Dametzstr. 38
Schimetta Consult Ziviltechniker Ges.m.b.H.
4020 Linz, Landwiedstr. 23
Contract Price
€ 875.000,00 net
Construction Time
11/2007 – 04/2008
Site Manager
Mr DI (FH) Gregor Dely
Arge Share in Euro / %
~ € 160.000,00 net
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]