Brief Description
Site management work for the extension of the existing plant in Pasching, consisting of:
Scope of Work
Excavation 9.200 m³
Concrete 5.800 m³
Formwork 9.600 m²
Concrete Reinforcement 425.000 kg
Monolithic Floor Slab 8.000 m²
FT Ceilings 1.900 m²
Cavity Walls 2.780 m²
FT Wall Slabs 1.900 m²
Client
Trumpf Maschinen Austria GmbH
4061 Pasching, Industriepark 24
Contact: Mr D.I. Thomas Saik
Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
4030 Linz, Kotzinastraße 4
Planning
Arch. Dipl.-Ing. Walter Deschka
2372 Giesshübl bei Wien, Hagenauertalstraße 42
Contract Price
€ 2.893.000,00 net
Construction Time
08/2007 – 05/2008
Site Managers
Mr Ing. Eduard Mayr (HF)
Mr Ing. Hannes Oberndorfer (Swietelsky)
Arge Share in Euro:
€ 1.446.500,00 / 50 %
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]