Site management work for the extension of the existing plant in Pasching, consisting of:

  • Foundations for steel hall of approx. 7,000 m², including monolithic floor slab with floor-heating.
  • Prefabricated parapets and prefabricated partition walls in the hall.
  • Construction of an approx. 60 m1-long, underground collector output and escape tunnel.
  • 2-storey office annexe (approx. 1,900 m²) in reinforced concrete construction.
  • Breaker cellar – 2nd upper storey for technical, social and seminar rooms approx. 3,170 m², partly in prefabricated construction and in-situ concrete construction.
  • Gas station, gas store and laser foundation

Scope of Work
Excavation  9.200 m³
Concrete  5.800 m³
Formwork  9.600 m²
Concrete Reinforcement  425.000 kg
Monolithic Floor Slab  8.000 m²
FT Ceilings  1.900 m²
Cavity Walls  2.780 m²
FT Wall Slabs  1.900 m²

Client
Trumpf Maschinen Austria GmbH
4061 Pasching, Industriepark 24
Contact: Mr D.I. Thomas Saik

Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
4030 Linz, Kotzinastraße 4

Planning
Arch. Dipl.-Ing. Walter Deschka
2372 Giesshübl bei Wien, Hagenauertalstraße 42

Contract Price
€ 2.893.000,00 net

Construction Time
08/2007 – 05/2008

Site Managers
Mr Ing. Eduard Mayr (HF)
Mr Ing. Hannes Oberndorfer (Swietelsky)

Arge Share in Euro:
€ 1.446.500,00 / 50 %

H&F Never Stands Still

At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]

Fit For A Lifetime

With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]

A Young Company Introduces Itself

H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]