Brief Description
Road-building in area of northern portal, length approx. 330 m and drainage. Area of southern portal approx. 1,100 m main route and drainage. Fill of lower substratum and 5 cm BTD 16 in the area of the tunnel – approx. 2,200 m. Construction of noise control wall in southern area.
Scope of Work
Removal of Asphalt 1.830 m³
Mech. Removal 15.000 m³
Embankment Fill 22.000 m³
Drainage Excavation 7.400 m³
Sewer and Drainage 3.250 m
UP 49.100 m²
Ungeb. TS 24.800 m³
BTHS32 13.100 to
AB11 1.300 to
SMA11 1.450 to
BTD16 2.500 to
Traunstein Shear Wall 265 m²
Kerbstone G5 950 m
Noise Control Wall Wooden Elements 126 m
Cable Protection Tubes 4.200 m
Gravel Shoulder 1.000 m³
Covering of Top Layer 5.050 m³
Client
ARGE Tunnel Henndorf
HF – Wayss & Freytag – HABAU
5302 Henndorf a. W., Sommerweg 1
Contact: Mr DI Holger Sawitzki (Project Manager, W & F)
Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
Salzburg Branch
Planning
Spirk & Partner + Geoconsult ZT GmbH
5020 Salzburg, Bayerhammerstraße 14
Contract Price
€ 3.020.000,- net
Construction Time
09/2008 – 07/2009
Site Manager
Mr Ing. Roland Kerschbaumer
Foremen
Mr Klaus Mayer, Mr Siegfried Laner
Arge Share in Euro / %
HF Salzburg in SUB for ARGE
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]