Brief Description
Construction of the appurtenant structures around the power towers on Böhmerwald-, Coulin- and Kärtnerstraße.
Scope of Work
Paving and Road Construction Work:
Road Bed Excavation Work approx. 1.350 m²
Cable Empty Tubing Block Section with 5 Cable Shafts approx. 700 lfm.
FFrost Wall and Mech. Stab. Substrata approx. 1.250 m³
Bituminous Substrata approx. 2.250 m²
Bituminous Surface Courses approx. 3.500 m²
Granite Kerbstones and Granite Blocks approx. 690 lfm.
Melted Asphalt Rill approx. 380 lfm.
Melted Asphalt approx. 200 m²
Client
POWER TOWER GmbH
4020 Linz, Blumauerstraße 29
Contractor
Held & Francke Baugesellschaft m.b.H. & Co KG
4030 Linz, Kotzinastraße 4
Planning
Prof. Kaufmann & Partner ZT-GmbH
4020 Linz, Pillweinstraße 30
Contact:
Mr Prof. Arch. DI Kaufmann Wolfgang (Planning)
Mr Ing. Zellinger Bernhard
Contract Price
approx. € 509.000,00 net
Construction Time
04/2008 – 09/2008
Site Manager
Mr Ing. Stefan Premm
With HABAU-FIT FOR A LIFETIME, we are taking an important step in the direction of being fit for work up to a ripe old age.[more]
H&F and Cteam have become HF Cteam. This group of companies is responsible for overhead pipeline construction in Austria.[more]
At Held und Francke the term "further training" is not just an empty phrase. Developing and also challenging personnel is of central importance for us.[more]